PROJECTS

BAPCO-MODERNISATION-PROGRAM-BMP

Services Provided

PLANT MAINTENANCE

Duration: December 2019 to December 2024

  • Comprehensive Insulation Solutions
    Scope of Work:
    Tasks
    Managed the entire lifecycle of insulation services including procurement, fabrication, supply, delivery, installation, and handover.
    Coverage Area
    Equipment and piping in BMP Mechanical works, specifically Area 6 (Units 005, 056, 061, 079, 094, 907) and Areas 4 & 5.
    Types
    Both HOT and COLD insulation and cladding.
    Compliance
    All work was performed according to BMP Project approved drawings, specifications, standards, procedures, and safety & quality requirements, adhering to project schedules.
  • Key Highlights:
    Complete Insulation Solution
    Provided end-to-end insulation services ensuring thermal efficiency and protection.
    Detailed Compliance
    Followed project-approved specifications to meet all quality and safety standards.
  • Scope of Work:
    Tasks
    Supplied, hired, erected, and dismantled scaffolding for BMP Mechanical works in Area 6 (Units 005, 056, 061, 079, 094, 907).
    Materials Used
    Tubes & Fittings and Cuplock systems 2500 Tons + high quality materials mobilized to BMP.
    Types of Scaffolding: Tower / Independent / Birdcage Scaffolding
    Mobile Scaffolding
    Suspended / Cantilever / Bridge Scaffolding
    Special Desing whereas required
  • Key Highlights:
    Versatile Solutions
    Provided various scaffolding types to meet different access and support needs.
    Safety & Efficiency
    Ensured all scaffolding services were executed with high safety standards and efficiency.
  • Scope of Work
    Tasks: Installation of refractory materials including Ceramic Fibre, Brick, and Casting for furnaces.
    Compliance: Work was performed as per BMP Project specifications, standards, procedures, and safety & quality requirements.
  • Key Highlights:
    High-Quality Refractory:
    Applied advanced refractory materials to ensure durability and performance in high-temperature environments.
    Adherence to Standards:
    Met all project-specific requirements and industry standards.
  • Scope of Work
    Tasks: Painting of concrete foundations of tanks & internal tank painting in Tank farm area
    Compliance: Performed in accordance with BMP Project specifications, standards, procedures, and safety & quality requirements.
  • Key Highlights:
    Durable Finishes:
    Applied coatings to ensure protection and aesthetics of surface
    Detailed Adherence:
    Followed all project guidelines to ensure high-quality and long-lasting results.
  • Scope of Work
    Tasks: Installation of fireproofing with lightweight concrete coating for steel structures.
    Compliance: Conducted as per BMP Project specifications, standards, procedures, and safety & quality requirements.
  • Key Highlights:
    Effective Fire Protection:
    Applied fireproofing solutions to enhance safety and compliance with fire protection regulations.
    Precision Application:
    Ensured all fireproofing work met the project’s detailed specifications and standards.